![Earned Value Management](https://www.projectengineer.net/wp-content/uploads/2017/02/earned-value-management.png)
Earned Value is a method used by project managers to calculate the current project status and predict future project performance. In this post we will outline each earned value formula.
- Planned Value (PV)
- Earned Value (EV)
- Actual Cost (AC)
- Schedule Variance (SV)
- Schedule Performance Index (SPI)
- Cost Variance (CV)
- Cost Performance Index (CPI)
- Budget at Completion (BAC)
- Estimate at Completion (EAC)
- Estimate to Complete (ETC)
- Variance at Completion (VAC)
- To Complete Performance Index (TCPI)
The first three are inputs obtained from project data. The rest are outputs calculated by the project manager which provide various information about the schedule and cost status of the project.
Planned Value (PV)
Also known as Budgeted Cost of Work Scheduled (BCWS), Planned Value is the amount of the task that is supposed to have been completed, in terms of the task budget. It is calculated from the project budget.
For example, if it’s Feb. 12 today, and the task is supposed to last from Feb. 10 to Feb. 20, it should be 20% complete. If the task budget is $10,000, PV = 20% x $10,000 = $2,000.
Earned Value (EV)
Also known as Budgeted Cost of Work Performed (BCWP), Earned Value is the amount of the task that is actually completed. It is also calculated from the project budget.
For example, if the actual percent complete is 25% and the task budget is $10,000, EV = 25% x $10,000 = $2,500.
Actual Cost (AC)
Also known as Actual Cost of Work Performed (ACWP), Actual Cost is the actual to-date cost of the task.
For example, if the actual cost is $3,500, AC = $3,500.
Schedule Variance (SV)
In this, the first output calculated in the earned value analysis, the project manager obtains a value which tells you the amount that the task is ahead or behind schedule.
- If SV is negative, the task is behind schedule.
- If SV is zero, the task is on schedule
- If SV is positive, the task is ahead of schedule.
In our example, SV = $2,500 – $2,000 = $500. This task is ahead of schedule.
Schedule Performance Index (SPI)
The SPI, similar to the SV, also indicates ahead or behind schedule but gives the project manager a sense of the relative amount of the variance. If you told me your project had a $500 schedule variance, this would mean drastically different things if your project was for building a backyard fence versus constructing a highrise building.
- If SPI < 1, the task is behind schedule
- If SPI = 1, the task is on schedule
- If SPI > 1, the task is ahead of schedule
In our example, SPI = $2,500 / $2,000 = 1.25. Therefore, the task is 25% ahead of schedule.
Cost Variance (CV)
Similar to the schedule variance, the Cost Variance tells the project manager how far the task is over or under budget.
- If CV is negative, the task is over budget
- If CV is zero, the project is on budget
- If CV is positive, the project is under budget
In our example, CV = $2,500 – $3,500 = -$1,000. The task is over budget. Note that the task can be ahead of schedule but over budget. Too much money has been spent compared to the amount of work that is currently complete.
Cost Performance Index (CPI)
The CPI, similar to the CV, also indicates over or under budget but gives the project manager a sense of the relative amount of the variance.
- If CPI < 1, the task is over budget
- If CPI = 1, the task is on budget
- If CPI > 1, the task is under budget
In our example, CPI = $2,500 / $3,500 = 0.71. Therefore, the task is 29% over budget.
Budget at Completion (BAC)
This one is easy. It is simply the total project budget, which is the aggregate of all of the task budgets.
In our example, if we assume the project has just that one task, BAC = $10,000.
Estimate at Completion (EAC)
This value tells the project manager what the overall project budget will be if everything else went according to plan. It is the extrapolation of the current project status to the end of the project. Because it is an extrapolation, it can be legitimately calculated in several ways. The project manager must make one of four assumptions:
- The reason for the variance is likely to continue. The project will continue on its previous path.
EAC = BAC/CPI
- The reason for the variance is not likely to continue. The project performance is expected to return to planned levels.
EAC = AC + (BAC – EV)
- When you feel the project’s future cost performance is likely to be impacted by both the past schedule performance as well as cost, you can use a hybrid.
EAC = AC + [(BAC – EV)/(SPI x CPI)]
- When you need to change the estimate because the initial assumptions were wrong.
EAC = AC + ETC
In our example, let’s say the reason for the negative cost variance is a snowstorm that delayed the project. It is not likely to affect the rest of the project, therefore EAC = $3,500 + ($10,000 – $2,500) = $11,000. This is the expected final budget.
Estimate to Complete (ETC)
This value tells the project manager how much money must be spent from this point forward to complete the project. Sometimes the project assumptions have changed and a new estimate must be produced instead of old performance metrics assumed.
- The project is expected to continue with the same performance in the future as the past.
ETC = EAC – AC
- The past project performance cannot be expected to continue. A new estimate is required.
ETC = new estimate
Variance at Completion (VAC)
This value tells the project manager the forecasted cost variance (CV) at the completion of the project. It is the extrapolation of the current project status, using the EAC method chosen.
- If VAC is negative, you need that much more money to complete the project.
- If VAC is positive, you will finish the project with that much of a surplus.
In our example, VAC = $10,000 – $11,000 = -$1,000. You will need an additional $1,000 to complete the project.
To Complete Performance Index (TCPI)
This value tells the project manager what CPI would be necessary to finish the project on budget. It gives an indication of how much efficiency needs to be found in the remainder of the project to make up for past negative variances.
If the project is required to finish within the original budget:
If the project budget is flexible to accommodate the past variance:
In our example, let’s assume there is no new money. The original budget is fixed and the project must make up the current negative cost variance. TCPI = ($10,000 – $2,500) / ($10,000 – $3,500) = 1.15. This means the project needs to find 15% efficiencies for the remainder to finish on budget.
Summary Table
Symbol | Name | Formula | Description | Interpretation of Result |
---|---|---|---|---|
Inputs | ||||
PV | Planned Value | The value of the portion of the task that is supposed to have been completed | ||
EV | Earned Value | The value of the portion of the task that is actually completed | ||
AC | Actual Cost | The actual cost of the task to date | ||
BAC | Budget at Completion | Total overall project budget (planned) | ||
Basic Outputs | ||||
SV | Schedule Variance | SV = EV – PV | The amount that the task is ahead or behind schedule, expressed as a task value | SV < 0 = behind schedule SV > 0 = ahead of schedule |
SPI | Schedule Performance Index | SPI = EV/PV | The amount that the task is ahead or behind schedule, expressed as a percentage of the task | SPI < 1 = behind schedule SPI > 1 = ahead of schedule |
CV | Cost Variance | CV = EV – AC | The amount that the task is over or under budget, expressed as a task value | CV < 0 = over budget CV > 0 = under budget |
CPI | Cost Performance Index | CPI = EV/AC | The amount that the task is ahead or behind schedule, expressed as a percentage of the task | CPI < 1 = over budget CPI > 1 = under budget |
Complex Outputs | ||||
EAC | Estimate at Completion |
|
The estimated project budget at the end of the project, given current project budget status | |
ETC | Estimate to Complete |
|
The expected cost to finish the project | |
VAC | Variance at Completion |
|
The expected cost variance at the end of the project, given current project status | VAC < 0 = over budget VAC > 0 = under budget |
TCPI | To Complete Performance Index |
|
The CPI required to complete the project on budget | TCPI < 1 = under budget TCPI > 1 = over budget |
Leave a Reply